[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147814":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1147814,801,2,"多选题","下列施工单位为避免进度受影响所做的工作，合理的是（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","检查和审核设计图纸符合现场条件",true,{"key":16,"text":17,"correct":14},"B","指正会审图纸中的交底不清楚问题",{"key":19,"text":20,"correct":21},"C","拒绝业主对图纸的修改",false,{"key":23,"text":24,"correct":21},"D","对设计内容进行变更",{"key":26,"text":27,"correct":14},"E","按施工图纸进行技术交底和培训","ABE","施工单位在项目实施的准备阶段进行进度控制的技术工作重点之一就是要做好施工图的审查工作，施工图审查的内容包括设计图纸与现场工程条件是否一致，设计交底是否清楚，是否全面熟悉施工图内容，是否存在影响工程正常施工的内容。作为施工单位应当要明确，建设单位可以进行施工图的变更或修改，而施工单位一般不能，只有具备充分理由如对工程使用或施工产生影响，方能向监理报告请求进行设计变更。因此，答案选择A、B、E。",{"id":6,"name":31,"category":32,"favorite":33},"一建矿业工程实务","建筑工程",0]