[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147813":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1147813,801,2,"多选题","通常，要加快一条巷道的施工进度，可考虑采用的手段有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","平行作业或平行施工方法",true,{"key":16,"text":17,"correct":18},"B","实现多个工作面的多头作业",false,{"key":20,"text":21,"correct":18},"C","一天24h连续作业",{"key":23,"text":24,"correct":18},"D","取消放炮后的通风T序",{"key":26,"text":27,"correct":14},"E","采用多台钻机同时作业","AE","一般井下巷道很难找到同时有多个工作面的情况，所以实现多个工作面的多头作业不合适(B)；一天24h作业是井下巷道作业的惯例，不能有提高原来进度计划的效果(C)；通风虽然是辅助工序，但是取消放炮后的通风是安全规程所不允许的(D)。因此答案应为A、E。",{"id":6,"name":31,"category":32,"favorite":33},"一建矿业工程实务","建筑工程",0]