[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147811":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1147811,801,2,"多选题","矿山工程进度计划编制的基本程序，正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","绘制初步网络计划在调查研究之前",false,{"key":16,"text":17,"correct":18},"B","确定方案在调查研究之后",true,{"key":20,"text":21,"correct":18},"C","划分工序在方案确定之后",{"key":23,"text":24,"correct":14},"D","确定初始网络图(或横道图)后就可以确定进度计划",{"key":26,"text":27,"correct":14},"E","编制进度计划和资源能力没有关系","BC","矿山工程进度计划编制的基本程序是：(1)调查研究；(2)确定方案；(3)划分工序并估算时间；(4)绘制网络图(或横道图)并优化、确定进度计划。优化就是判别资源的可行性。如果超过了资源的可行性，就要进行调整，要将施工高峰错开，削减资源用量高峰；或者改变施工方法，减少资源用量。这时就要增加或改变某些组织逻辑关系，在保证工期满足要求的同时，满足资源的计划用量要求；然后重新绘制时间坐标网络图。",{"id":6,"name":31,"category":32,"favorite":33},"一建矿业工程实务","建筑工程",0]