[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147810":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1147810,801,2,"多选题","建井总工期是以下（ ）的工期之和。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工准备期",true,{"key":16,"text":17,"correct":18},"B","矿井投产工期",false,{"key":20,"text":21,"correct":14},"C","矿井竣工工期",{"key":23,"text":24,"correct":18},"D","巷道施工期",{"key":26,"text":27,"correct":18},"E","井筒施工工期","AC","矿井建设的工期概念，包括施工准备期、矿井投产工期、矿井竣工工期、建井总工期等内容。其中施工准备期是指矿井从完成建设用地的征购工作，施工人员进场，开始场内施工准备工作之日起，至项目正式开工为止叫施工准备期；矿井投产工期是指从项目正式开工(矿井以关键路线上任何一个井筒破土动工)之日起到部分工作面建成，并经试运转，试生产后正式投产所经历的时间，为矿井投产工期；矿井竣工工期是从项目正式开工之日起到按照设计规定完成建设工程，并经过试生产，试运转后正式竣工、交付生产所经历的时间为矿井竣工工期(或称为建井工期)；建井总工期是指矿井施工准备工期与矿井竣工工期之和构成矿井建设总工期(或称建井总工期)。",{"id":6,"name":31,"category":32,"favorite":33},"一建矿业工程实务","建筑工程",0]