[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147809":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1147809,801,2,"多选题","以下对影响矿业工程项目工期的分析，正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","矿井实际地质条件变复杂会延长工期",true,{"key":16,"text":17,"correct":18},"B","工期影响与施工单位的资金储备无关",false,{"key":20,"text":21,"correct":18},"C","保证设备供应不影响进度的措施就是做到设备及时到位",{"key":23,"text":24,"correct":14},"D","技术措施不当是影响工期的重要因素",{"key":26,"text":27,"correct":14},"E","对意外情况有预案能减少不利因素的影响","ADE","施工单位在参与项目时应有一定资金储备，以备必要时的垫付以及可能出现的额外付出，否则将有可能造成工程中断(B)；设备及时到位是避免物资供应条件影响工期的一个重要因素，但是物资供应不仅要求及时到位，还要求到位物资的质量，如材料的合格、设备能正常运转等满足要求，否则同样会影响工程进程，这相对更复杂些，要求建立有物资供应的质量保证体系(C)。故答案应为A、D、E。",{"id":6,"name":31,"category":32,"favorite":33},"一建矿业工程实务","建筑工程",0]