[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147808":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1147808,801,2,"多选题","在施工准备阶段中，施工单位确定分包商后尚应完成（ ）等协调工作。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","检查和落实分包商的资质条件",false,{"key":16,"text":17,"correct":18},"B","建立与分包商的工作联系制度",true,{"key":20,"text":21,"correct":18},"C","检查分包商的项目进度计划",{"key":23,"text":24,"correct":18},"D","提供和落实分包项目的施工图纸",{"key":26,"text":27,"correct":18},"E","审核分包商的施工安全规程","BCDE","检查和落实分包商的资质条件是确定分包商之前应该完成的工作。",{"id":6,"name":31,"category":32,"favorite":33},"一建矿业工程实务","建筑工程",0]