[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147806":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1147806,801,2,"多选题","工业广场地面施工总平面布置的设计依据，包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工程项目的总平面设计图纸",true,{"key":16,"text":17,"correct":18},"B","井筒地质检查钻孔位置设计方案",false,{"key":20,"text":21,"correct":14},"C","工业广场工程地质与水文地质图",{"key":23,"text":24,"correct":18},"D","地质构造图",{"key":26,"text":27,"correct":14},"E","临时工程建筑项目表","ACE","因为是工业广场的地面布置，地质构造一般不涉及，而工程地质与水文地质资料是必须的。井筒检查钻孔此时已经完成，一般不影响工业广场布置。施工总平面图中，临时工程布置是重要的内容，因此必须有临时建筑的项目表。",{"id":6,"name":31,"category":32,"favorite":33},"一建矿业工程实务","建筑工程",0]