[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147805":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1147805,801,2,"多选题","施工准备阶段要编制的计划和相应落实的工作内容包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","劳力需要量计划和生活设施准备",true,{"key":16,"text":17,"correct":14},"B","材料需要量计划和场地准备",{"key":19,"text":20,"correct":21},"C","施工机械需要量计划和安装设备进场工作",false,{"key":23,"text":24,"correct":14},"D","施工图供应计划和会审工作安排",{"key":26,"text":27,"correct":21},"E","工业场地用地计划和购置工作","ABD","施工机械是施工需要，与设备无关，后者是关于生产设备的安装内容。工业场地用地计划和购置内容不属于施工单位，且应在项目招投标完成前完成。因此本题答案应为A、B、D。",{"id":6,"name":31,"category":32,"favorite":33},"一建矿业工程实务","建筑工程",0]