[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147804":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1147804,801,2,"多选题","矿业工程施工准备工作的内容包括（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","技术准备",true,{"key":16,"text":17,"correct":14},"B","工程准备",{"key":19,"text":20,"correct":14},"C","物资准备",{"key":22,"text":23,"correct":14},"D","劳动力准备",{"key":25,"text":26,"correct":27},"E","资质与法律文件准备",false,"ABCD","矿业工程施工准备工作包括：技术准备、工程准备、物资准备、劳动力的准备、协作工作等。技术准备指施工技术条件落实、图纸准备、编制技术文件、技术交底等；工程准备指施工场地勘察和准备；物资准备指材料、设备供应计划及计划落实；劳动准备即施工队伍准备并进场、落实技术交底及生产、安全制度；协作工作包括建立各协作关系、做好分包的相关工作等。",{"id":6,"name":31,"category":32,"favorite":33},"一建矿业工程实务","建筑工程",0]