[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147802":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1147802,801,2,"多选题","矿业工程施工顺序的安排中，需要优先考虑的项目是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","临时工程",false,{"key":16,"text":17,"correct":18},"B","关键工程",true,{"key":20,"text":21,"correct":18},"C","井下供电系统",{"key":23,"text":24,"correct":18},"D","井下排水系统",{"key":26,"text":27,"correct":18},"E","通风系统","BCDE","矿业工程施工中，通常井下供电、通风、排水等涉及矿井安全保障的项目应优先安排，特别是水害突出的矿井、高瓦斯矿井，经常会以风定产、以排水能力确定掘进工程等。",{"id":6,"name":31,"category":32,"favorite":33},"一建矿业工程实务","建筑工程",0]