[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147801":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1147801,801,2,"多选题","属于矿井项目工程施工组织设计的技术经济指标的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工准备工期长短",false,{"key":16,"text":17,"correct":18},"B","井筒及主要巷道月进度指标",true,{"key":20,"text":21,"correct":18},"C","建筑安装工人劳动生产率",{"key":23,"text":24,"correct":14},"D","大型机械台班用量及费用",{"key":26,"text":27,"correct":18},"E","临时工程预算占矿井建筑安装工程总投资的比重","BCE","矿井工程的工期指标应采用建井总工期，机械台班用量和费用属于地面其他工程的考核经济技术指标。",{"id":6,"name":31,"category":32,"favorite":33},"一建矿业工程实务","建筑工程",0]