[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147798":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1147798,801,2,"多选题","关于井筒工程的施工顺序，以下考虑正确的是（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","主井工作量一般比较大，因此主井往往先于副井开工",true,{"key":16,"text":17,"correct":14},"B","主井与副井同时开工要求的人力、财力投入比较大",{"key":19,"text":20,"correct":21},"C","当风井与主、副井距离比较远时，要求其较主、副井先开工",false,{"key":23,"text":24,"correct":21},"D","要求主井与副井同时到底的好处是可以比较两队的施工水平",{"key":26,"text":27,"correct":21},"E","主井在副井建成后再施工可给主井提供可靠的地质资料","AB","对于“副井建成后主井再施工可以为主井提供可靠的地质资料”的说法，因为有井筒检查钻孔的资料，就变得不必要；且即使需要，也可以提前部分时间即可达到此目的，而不必等建完副井后再建主井。风井距离远近和安排其与主、副井施工的先后没有直接关系。",{"id":6,"name":31,"category":32,"favorite":33},"一建矿业工程实务","建筑工程",0]