[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147784":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1147784,801,2,"多选题","影响施工测量控制网精度要求的因素有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","测量方法",false,{"key":16,"text":17,"correct":18},"B","建筑材料",true,{"key":20,"text":21,"correct":18},"C","结构形式",{"key":23,"text":24,"correct":18},"D","施工方法",{"key":26,"text":27,"correct":14},"E","测量仪器要求","BCD","一般，施工测量控制网的精度由建筑物的限差决定。要求的精度过高，则增加测量工作量或工作难度，而低于建筑限差精度要求，就不能满足施工质量要求。决定建筑限差的因素有工程性质、结构形式、建筑材料种类、施工方法等内容。不同建筑物的建筑条件有区别，所以对一个施工测量控制网而言，涉及的建筑物不同其测量精度就是有区别的。但是，测量方法和测量仪器都不应该影响工程限差要求，所以本题答案应该为B、C、D",{"id":6,"name":31,"category":32,"favorite":33},"一建矿业工程实务","建筑工程",0]