[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147774":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1147774,801,2,"多选题","矿业工程施工测量的工作内容包括有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","测绘矿区地形图及矿界",true,{"key":16,"text":17,"correct":18},"B","建立测图控制网以布置工程位置",false,{"key":20,"text":21,"correct":14},"C","完成井下巷道、硐室等工程的竣工测量",{"key":23,"text":24,"correct":14},"D","承担地面工程质量检查测量",{"key":26,"text":27,"correct":14},"E","提供矿山安全的重要的测量信息","ACDE","矿业工程测量工作的内容主要包括测绘矿区地形图及矿界、完成地上、地下各种工程的施工和竣工测量、绘制各种采掘工程图和矿山专用图、承担井巷支护工程、采掘工程的质量检查和验收工作、评价矿井采、掘工程对地面环境影响和提供矿山安全的相关重要信息等。这些工作的绝大部分由施工测量完成，但是测图控制网不是施工测量完成，虽然也可以利用测图控制网来布设施工控制网，一般不用它来布设工程位置，通常其精度不易满足施工测量要求。故本题答案为A、C、D、E",{"id":6,"name":31,"category":32,"favorite":33},"一建矿业工程实务","建筑工程",0]