[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147748":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1147748,801,2,"多选题","冻结法凿井时，冻结后的井筒开挖时间应符合( )条件。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","水文孔水位规律上升",true,{"key":16,"text":17,"correct":14},"B","测温温度符合设计要求",{"key":19,"text":20,"correct":21},"C","井筒内部岩土已有冻结",false,{"key":23,"text":24,"correct":14},"D","井筒施工条件已具备",{"key":26,"text":27,"correct":21},"E","冻结壁不再有冻结膨胀","ABD","通常，冻结后井筒开挖时间选择以冻结壁已形成而又尚未冻至井筒范围以内时开挖最为理想。井筒开挖，必须具备的条件：1．水文观测孔内的水位，应有规律上升，并溢出孔口；2．测温口的温度已符合设计规定；3．地面提升、搅拌系统等施工条件已具备。",{"id":6,"name":31,"category":32,"favorite":33},"一建矿业工程实务","建筑工程",0]