[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147722":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1147722,801,2,"多选题","立井井筒施工的掘进段高，由( )等因素确定。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","井筒穿过岩层的性质",true,{"key":16,"text":17,"correct":14},"B","涌水量大小",{"key":19,"text":20,"correct":21},"C","井壁结构的形式",false,{"key":23,"text":24,"correct":14},"D","井筒施工速度",{"key":26,"text":27,"correct":14},"E","临时支护形式","ABDE","井筒掘进段高，是根据井筒穿过岩层的性质、涌水量大小、临时支护形式、井筒施工速度来确定的。岩性条件差时，围岩的稳定时间短，如果没有临时支护，则肯定不能采用岩壁裸露时间长的段高。涌水量高时，裸露的段高越高，涌水就越严重，对围岩稳定性的影响越严重，也不能有很长的段高。井筒施工速度也是控制裸露岩帮时间的关键性因素。井壁结构由设计确定，虽然它的砌筑快慢会影响岩壁的裸露时间，但是这部分影响内容由施工速度考虑；也就是说，它不直接影响井帮岩壁的稳定状况。因此，该题的A、B、D、E",{"id":6,"name":31,"category":32,"favorite":33},"一建矿业工程实务","建筑工程",0]