[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147702":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1147702,801,2,"多选题","关于土层锚杆施工时对土层锚杆技术要求，说法正确的有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","间排距应不小于2．0m×2．5m",true,{"key":16,"text":17,"correct":18},"B","上覆层厚度不大于2m",false,{"key":20,"text":21,"correct":18},"C","锚固段长度应在2m以上",{"key":23,"text":24,"correct":18},"D","预应力应和设计受拉荷载一致",{"key":26,"text":27,"correct":14},"E","倾斜锚杆的角度宜在15°～35°的范围","AE","土层锚杆的布设方式和其作用效果很有关系，本题的内容涉及土层锚杆的一些重要参数。在土层锚杆中，有的参数值是根据锚杆的荷载大小由设计确定，有的是根据结构要求确定。一般，土层锚杆的问排距不应小于2．0m×2．5m；锚杆的上覆层厚度不应小于4m；锚杆的锚固长度不应小于4m；锚杆的倾斜角度宜在15。～35。的范围；锚杆的预应力一般是荷载设计值的0．5～0．6的范围。以上这些多数是结构要求的重要参数，有的是经验数据，但它们都在施工中起到重要作用。",{"id":6,"name":31,"category":32,"favorite":33},"一建矿业工程实务","建筑工程",0]