[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147673":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1147673,801,2,"多选题","关于防水涂料的施工，说法正确的有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","涂料施工前应先对基面处理",true,{"key":16,"text":17,"correct":18},"B","同一防水层要求连续刷涂三次涂料",false,{"key":20,"text":21,"correct":14},"C","第二层涂料的涂刷应与第一层垂直",{"key":23,"text":24,"correct":18},"D","同层涂膜的相互搭接不应大于5mm",{"key":26,"text":27,"correct":14},"E","防水层施工后应通过渗漏试验","ACE","关于防水涂料的施工，要求施工前对基层进行认真处理，去除表面积灰、油污、铁锈等；涂刷应分多次完成，后一次必须等前一层干燥后进行，第二层涂料的涂刷方向应与第一层垂直，同层涂膜的相互搭接不应小于5mm；涂料层施工完成后，要通过渗漏的合格试验，试验前还应做好防水层的保护工作。",{"id":6,"name":31,"category":32,"favorite":33},"一建矿业工程实务","建筑工程",0]