[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147653":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1147653,801,2,"多选题","冻结井筒的混凝土施工中的合理措施有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","限制混凝土搅拌环境的最低温度",false,{"key":16,"text":17,"correct":18},"B","限制混凝土料的入模最低温度",true,{"key":20,"text":21,"correct":14},"C","适当提高水灰比以便于溜灰管下料",{"key":23,"text":24,"correct":18},"D","C40以上混凝土采用吊桶下料",{"key":26,"text":27,"correct":18},"E","对搅拌机进行预热","BDE","冻结井筒混凝土施工属于低温混凝土施工。按照低温混凝土施工方法和要求，为保证混凝土人模温度，可以用热水(水温不宜高于60～80℃)进行水泥搅拌，也可以对砂、石加温，或对搅拌机进行预热。《煤矿井巷工程施工规范》GB 50511--2010规定，采用冻结法凿井时，混凝土的人模温度以15℃为宜；低温季节施工时的人模温度应不低于10℃(高温季节施工时的人模温度应不高于30℃)。规定的向井下输送混凝土的方式是：强度小于或等于C40的混凝土可采用溜灰管下料，但应采取防止混凝土离析的措施，显然不能以提高水灰比的方式实现溜灰管下料；强度大于C40的混凝土宜采用底卸式吊桶下料；控制搅拌施工的环境温度难以实现；井筒冻结施工的低强度等级混凝土可以采用溜灰管下料。因此选项按A、C要求施工不合理。",{"id":6,"name":31,"category":32,"favorite":33},"一建矿业工程实务","建筑工程",0]