[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147631":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1147631,801,2,"多选题","矿业工程竣工资料汇总、组卷的方法是（）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","工程质量控制资料按单位工程、分部工程、专业、阶段等汇总、组卷",true,{"key":16,"text":17,"correct":14},"B","工程观感质量检查资料按单位工程、专业等汇总、组卷",{"key":19,"text":20,"correct":14},"C","竣工图按单位工程、专业等汇总、组卷",{"key":22,"text":23,"correct":24},"D","验收合格后，竣工资料移交时间由发包方确定",false,{"key":26,"text":27,"correct":24},"E","每张移交图纸上均应有双方签字、盖章","ABC","2020版教材页码P355 工程竣工资料中的工程质量控制资料按单位工程、分部工程、专业、阶段等为单位汇总、组卷；工程质量验收评定资料、工程观感质量检查资料按单位工程、专业等汇总、组卷；竣工图按单位工程、专业等汇总、组卷。",{"id":6,"name":31,"category":32,"favorite":33},"一建矿业工程实务","建筑工程",0]