[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147626":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1147626,801,2,"多选题","下列关于确定工程变更价款的说法，正确的是（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","承包人应在工程变更确定后14d内，提出变更工程价款的报告",true,{"key":16,"text":17,"correct":14},"B","监理工程师应在收到变更工程价款报告之日起14d内予以确认",{"key":19,"text":20,"correct":21},"C","工程变更价款最终应由业主确认",false,{"key":23,"text":24,"correct":21},"D","监理工程师不同意承包人提出的变更价款的，则承包人应予以接受",{"key":26,"text":27,"correct":21},"E","工程变更价款最终应由承包人确认","AB","2020版教材页码P343-344 承包人首先在工程变更确定后14D内，提出变更工程价款的报告，经工程师确认后调整合同价款，在双方确定变更后14D内承包人不向工程师提出变更工程价款报告的，视为该项变更不涉及合同价款的变更。工程师应在收到变更工程价款报告之日起14D内予以确认，工程师无正当理由不确认的，自变更工程价款报告送达之日起14D后视为变更工程价款报告已被确认。工程师不同意承包人提出的变更价款的，按合同规定的有关争议解决的约定处理。另外，工程变更价款最终应由承、发包双方共同确认。",{"id":6,"name":31,"category":32,"favorite":33},"一建矿业工程实务","建筑工程",0]