[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147590":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1147590,801,2,"多选题","矿山工程进度拖延时，正确的事后措施包括有（）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","分析原因和影响工期程度",true,{"key":16,"text":17,"correct":14},"B","经过业主同意，删减工程量或工程范围",{"key":19,"text":20,"correct":14},"C","采用外包方法请专业公司帮助解决",{"key":22,"text":23,"correct":14},"D","分析网络计划，根据影响工期与否选择是否调整资源投入",{"key":25,"text":26,"correct":27},"E","集中到验收前一并处理",false,"ABCD","2020版教材页码P188-191 进度拖延的事后措施，其最关键内容的是要分析引起拖延的原因，并针对原因采取措施；还可以采取投入更多的资源加速活动、采取措施保证后期的活动按计划执行；分析进度网络，找出有工期延迟的路径；改进方法和技术提高劳动生产率；或者征得业主的同意后，缩小工程的范围，甚至删去一些工作包（或分项工程）；或采用外包策略，让更专业的公司完成一些分项工程。",{"id":6,"name":31,"category":32,"favorite":33},"一建矿业工程实务","建筑工程",0]