[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147588":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1147588,801,2,"多选题","建井总工期是以下（）的工期之和。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工准备期",true,{"key":16,"text":17,"correct":18},"B","矿井投产工期",false,{"key":20,"text":21,"correct":14},"C","矿井竣工工期",{"key":23,"text":24,"correct":18},"D","巷道施工期",{"key":26,"text":27,"correct":18},"E","井筒施工工期","AC","2020版教材页码P173-174 矿井施工准备工期与矿井竣工工期之和构成矿井建设总工期（或称建井总工期）。",{"id":6,"name":31,"category":32,"favorite":33},"一建矿业工程实务","建筑工程",0]