[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147582":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1147582,801,2,"多选题","井筒施工中的井身工程，其分项工程包括（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","井颈工程",false,{"key":16,"text":17,"correct":18},"B","掘进工程",true,{"key":20,"text":21,"correct":18},"C","模板工程",{"key":23,"text":24,"correct":14},"D","支护工程",{"key":26,"text":27,"correct":18},"E","钢筋工程","BCE","2020版教材页码P146-147 注意，所谓分项工程，就是组成分部工程中的工序、工种内容，它没有独立发挥生产能力和独立施工的条件，但可以独立进行工程价款的结算。分项工程一般可以根据施工的规格形状、材料、施工方法等内容统一计算工程量和进行结算，或者说，同一个分项工程可用同一计量单位统计工作量和计价。根据这些定义的内容可知，掘进工程、模板工程、钢筋工程属于分项工程，井颈工程是井筒不同部位的工程内容，不属于分项工程；支护工程虽然是一个工序内容，但是因为支护的形式有多种多样，所以不能单独用“支护工程”内容来进行统一计算其内含的工作量和计价。",{"id":6,"name":31,"category":32,"favorite":33},"一建矿业工程实务","建筑工程",0]