[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147477":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1147477,801,2,"多选题","桩基施工时，正确的打桩的顺序有（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","先深后浅",true,{"key":16,"text":17,"correct":18},"B","先浅后深",false,{"key":20,"text":21,"correct":14},"C","先大后小",{"key":23,"text":24,"correct":18},"D","先小后大",{"key":26,"text":27,"correct":14},"E","先长后短","ACE","2020版教材页码P71-76 选择打桩顺序是否合理，直接影响打桩进度和施工质量。确定打桩顺序时要综合考虑到桩的密集程度、基础的设计标高、现场地形条件、土质情况等。当基坑不大时，一般应从中问向两边或四周进行；当基坑较大时，应分段进行；应避免自外向内，或从周边向中间进行的情况。当桩基的设计标高不同时，打桩顺序宜先深后浅。当桩的规格不同时，打桩顺序宜先大后小、先长后短。",{"id":6,"name":31,"category":32,"favorite":33},"一建矿业工程实务","建筑工程",0]