[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147436":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1147436,801,2,"多选题","关于混凝土井壁施工模板的说法，正确的是（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","长段井壁施工可采用滑升模板",true,{"key":16,"text":17,"correct":18},"B","喷混凝土施工要采用木模板",false,{"key":20,"text":21,"correct":14},"C","掘砌混合作业采用金属整体移动模板",{"key":23,"text":24,"correct":14},"D","掘进段高确定整体金属模板高度",{"key":26,"text":27,"correct":18},"E","炮眼深度1m时整体金属模板高度应有1.5m以上","ACD","喷混凝土施工不需要模板，故B错误；炮眼深度1m时整体金属模板高度应有1.5m不合格。E不正确。此题正确项ACD。",{"id":6,"name":31,"category":32,"favorite":33},"一建矿业工程实务","建筑工程",0]