[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147390":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1147390,801,2,"多选题","下列关于基坑开挖的说法，正确的是（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","场地开挖一般采取由上而下、分块分段分层进行",true,{"key":16,"text":17,"correct":18},"B","相邻基坑开挖时应先浅后深或同时进行",false,{"key":20,"text":21,"correct":14},"C","在基坑边缘上侧堆土或材料以及移动施工机械时，应与基坑边缘保持1m以上距离",{"key":23,"text":24,"correct":18},"D","填土应按不同土透水性从小到大，自下而上分层回填",{"key":26,"text":27,"correct":18},"E","填土压实的分层厚度、压实遍数只与压实机械的功率有关，与填土含水情况无关","AC","相邻基坑开挖应先深后浅或同时进行，故B错误；填土应将透水性大的土置于透水性小的土之下，故D错误；填土压实的分层厚度、压实遍数与填土含水情况有关，影响夯实和碾压遍数。所以E错误。应选AC。",{"id":6,"name":31,"category":32,"favorite":33},"一建矿业工程实务","建筑工程",0]