[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147317":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1147317,801,2,"多选题","矿山项目决策阶段影响工程投资的因素有（??）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","市场因素",true,{"key":16,"text":17,"correct":14},"B","资源条件因素",{"key":19,"text":20,"correct":14},"C","技术因素",{"key":22,"text":23,"correct":14},"D","环境因素",{"key":25,"text":26,"correct":27},"E","总平面设计",false,"ABCD","制约项目规模合理化的因素有矿产资源和资源条件因素、市场因素、技术因素、环境因素等。",{"id":6,"name":31,"category":32,"favorite":33},"一建矿业工程实务","建筑工程",0]