[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147253":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1147253,801,2,"多选题","矿业工程的单项工程施工组织设计的编制依据包括有（??）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","合同或协议",true,{"key":16,"text":17,"correct":14},"B","工程总概算",{"key":19,"text":20,"correct":21},"C","施工图设计",false,{"key":23,"text":24,"correct":14},"D","地质精查报告",{"key":26,"text":27,"correct":21},"E","企业定额","ABD","施工组织设计的基本要求就是要依据合同或协议，同时应有单项工程的初步设计和相应的总概算，施工图设计是单位工程施工组织设计所需要的；而地质精查报告是矿井工程必须的内容；企业定额只能作为编制施工组织设计的参考，不能依据此作为凭证。",{"id":6,"name":31,"category":32,"favorite":33},"一建矿业工程实务","建筑工程",0]