[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147088":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1147088,801,1,"单选题","工程进度交换图纸不包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","井上下进度对照图",true,{"key":16,"text":17,"correct":18},"B","工业场地建筑工程交换图",false,{"key":20,"text":21,"correct":18},"C","巷道工程施工交换图",{"key":23,"text":24,"correct":18},"D","井筒工程施工交换图","工程进度交换图纸是用于上级机关掌握施工进度和工程情况及其变化，包括地质、水文条件的变化，施工方案的重大改变，安全、质量事故等影响正常施工的因素，所实行的一种特有的工程图纸交换制度。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]