[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147078":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1147078,801,1,"单选题","下列不属于发包人违约的情况的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","自然条件变化",true,{"key":16,"text":17,"correct":18},"B","发包人更改设计",false,{"key":20,"text":21,"correct":18},"C","发包人工作不力违约",{"key":23,"text":24,"correct":18},"D","工程师指令或失误","发包人违约的情况常见的有：(1)未按照约定的时间和要求提供原材料、设备、场地、资金、技术资料；(2)因发包人的原因致使工程中途停建、缓建；(3)因发包人变更计划，提供的资料不准确，导致返工、停工或者修改设计；(4)监理发出错误指令导致工程施工失误；(5)不按时支付工程款。因此，答案为A。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]