[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147068":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1147068,801,1,"单选题","项目与风险情况有关联是因为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目有明确的不利结果",false,{"key":16,"text":17,"correct":18},"B","项目的结果不明确",true,{"key":20,"text":21,"correct":14},"C","项目的合同已经有风险条款",{"key":23,"text":24,"correct":14},"D","干项目就是冒险","如主体仍介入肯定有不利结果的项目，那不是风险的问题，是“自投罗网”(A选项)；项目的合同已经有风险条款，这是项目存在风险的结果，不能作为项目与风险存在关联的原因，风险条款仅仅是规避风险的一种措施(C选项)；冒险是去干确认有危险的事情，和风险的含义不同(D选项)；项目与风险有关是因为项目存在某种不利条件可能来临的不利事情，这就是项目结果不确定的风险的含义(B选项)。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]