[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147066":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1147066,801,1,"单选题","在下列状况中，承包商应向发包商追究损失的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","因停电6h的误工",false,{"key":16,"text":17,"correct":14},"B","因承包方采用新技术增加的费用",{"key":19,"text":20,"correct":14},"C","因发包方耽误使承包方延长2d工作",{"key":22,"text":23,"correct":24},"D","因第三方未完成“三通一平”的延误",true,"停电8H或以上的误工可以索赔，A选项停电为6H，不属于可索赔之列；承包方采用新技术(B)应视是否被发包方认可，如自行采用则也不被认为可以索赔；使承包方工时增加2D(C)的索赔要由是否影响总工期来决定，如不影响则不能索赔；“三通一平”是发包方的责任，第三方及其工作由发包方安排，因此第三方工程对承包方进场的影响仍应由发包方负责，故合理的选项应为D。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]