[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147057":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1147057,801,1,"单选题","根据《建设工程工程量清单计价规范》GB50500—2013，编制工程量清单时，计日工表中的人工应按（ ）列项。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工种",true,{"key":16,"text":17,"correct":18},"B","职称",false,{"key":20,"text":21,"correct":18},"C","职务",{"key":23,"text":24,"correct":18},"D","技术等级","编制工程量清单时，计日工表中的人工应按工种，材料和机械应按规格、型号详细列项。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]