[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147049":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1147049,801,1,"单选题","符合列入工程量清单中暂估价的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","必然发生、暂时不能确定价格的材料金额",true,{"key":16,"text":17,"correct":18},"B","可能发生的材料金额",false,{"key":20,"text":21,"correct":18},"C","一种用于参考或比较用的材料金额",{"key":23,"text":24,"correct":18},"D","双方未能商定的材料金额","“暂估价”是指发包人在工程量清单或预算书中提供的用于支付必然发生但暂时不能确定价格的材料、工程设备的单价、专业工程以及服务工作的金额。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]