[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147046":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1147046,801,1,"单选题","下列工作中，不属于施工项目成本目标动态控制程序中的工作是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","目标分解",false,{"key":16,"text":17,"correct":18},"B","目标计划值搜集",true,{"key":20,"text":21,"correct":14},"C","目标计划值与实际值比较",{"key":23,"text":24,"correct":14},"D","采取措施纠偏","项目成本目标动态控制的程序中，包括目标实际值的搜集而不是计划值的搜集，故选项B不属于程序之中，故选B。其他三个选项均属于目标动态控制程序。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]