[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147043":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1147043,801,1,"单选题","某单位建筑工程初步设计深度不够，不能准确地计算工程量，但工程采用的技术比较成熟而又有类似指标可以利用时，编制该工程设计概算宜采用的方法是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","扩大单价法",false,{"key":16,"text":17,"correct":14},"B","类似工程换算法",{"key":19,"text":20,"correct":14},"C","生产能力指数法",{"key":22,"text":23,"correct":24},"D","概算指标法",true,"有类似的指标可以利用，所以编制设计概算采用概算指标法最合适。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]