[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147041":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1147041,801,1,"单选题","对于矿业工程项目而言，制约项目规模大小的首要因素是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","市场因素",false,{"key":16,"text":17,"correct":14},"B","环境因素",{"key":19,"text":20,"correct":14},"C","技术因素",{"key":22,"text":23,"correct":24},"D","矿产资源因素",true,"矿产资源的属性是国家所有，资源开发与否、开发规模大小首先由国家需要决定，在国家对矿产资源开发的规划基础上，进行矿产资源的开发；其次，开发的规模大小，还受资源条件所决定，由所开采的矿产资源储量多少所决定。储量少不能建设成为大规模的矿山项目；储量大，为建设大规模矿山企业提供基本条件。最后决定矿山规模时，要考虑环境因素、市场因素、技术因素等条件，考虑经济效果，以获得最大的利益。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]