[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147037":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1147037,801,1,"单选题","招标人应根据相关工程的工期定额合理计算工程，压缩的工期天数不得超过定额工期的（ ），超过者，应在招标文件中明示增加赶工费用。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","10％",false,{"key":16,"text":17,"correct":14},"B","15％",{"key":19,"text":20,"correct":21},"C","20％",true,{"key":23,"text":24,"correct":14},"D","25％","《建设工程工程量清单计价规范》GB50500--2013规定：“招标人应依据相关工程的工期定额合理计算工期，压缩的工期天数不得超过定额工期的20％，超过者应在招标文件中明示增加赶工费”。压缩工期超过定额工期的20％，需要事先明示。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]