[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147032":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1147032,801,1,"单选题","当工序成本没有超支时，引起实际开支与计划不符的原因是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","因施工发生困难",false,{"key":16,"text":17,"correct":14},"B","施工质量出现偏差",{"key":19,"text":20,"correct":21},"C","施工进度与计划不符",true,{"key":23,"text":24,"correct":14},"D","设备购置不当","施工成本的实际开支与计划不相符，往往是由两个因素引起的，一是在某道工序上的成本开支超出计划；二是某道工序的施工进度与计划不符。因此，要想找出成本变化的真正原因，必须与进度计划的适时更新相结合。本题中因为工序成本没有超支，故造成成本超支的应该是进度计划与实际不符。施工发生困难与成本超支没有直接关系，施工质量及设备购置问题也不应列人工序费用。故答案应为C。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]