[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146978":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1146978,801,1,"单选题","立井井筒工程竣工验收时，通常不检查（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","井筒中心坐标和断面大小",false,{"key":16,"text":17,"correct":14},"B","井壁质量",{"key":19,"text":20,"correct":14},"C","井筒涌水量的大小",{"key":22,"text":23,"correct":24},"D","通过井筒的风速大小",true,"立井井筒竣工后，应该检查井筒的坐标、标高、深度以及与井筒相连的巷道口标高和方位，检查井壁质量和井筒总涌水量，井筒断面大小和井壁垂直度，隐蔽工程记录等。通过井筒的风速大小只要有井筒的断面数据即可获得，不必单独进行检查。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]