[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146974":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1146974,801,1,"单选题","锚杆安装时其外露太长、托盘不能贴紧岩面的工序衔接问题是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","锚杆孔的深度未检查",true,{"key":16,"text":17,"correct":18},"B","锚杆预紧力不够",false,{"key":20,"text":21,"correct":18},"C","锚杆长度过长",{"key":23,"text":24,"correct":18},"D","锚杆固结时间太早","本题是关系工序质量控制问题。工序质量控制要特别关注的一项工作是工序间衔接应满足要求，控制上下工序间的交接工作。本题的背景是锚杆外露长、托盘无法紧贴岩面。与锚杆安装的上道衔接工序是锚杆孔质量，影响托盘不能紧贴的锚杆孔质量问题是孔深度不够，这是衔接锚杆安设应检查的内容(A)；锚杆预紧力(B)是锚杆安装工序自身的质量内容；锚杆固结(D)与锚杆紧贴无直接关系；锚杆长度的检查应是锚杆材质、规格检查时完成，也不是锚杆安设前的衔接内容。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]