[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146958":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1146958,801,1,"单选题","下列进度控制措施中，属于组织管理措施的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","优选施工方案",false,{"key":16,"text":17,"correct":14},"B","采用新技术、新工艺",{"key":19,"text":20,"correct":21},"C","加强总包与分包单位间的协调工作",true,{"key":23,"text":24,"correct":14},"D","编制资源需求计划","矿业工程项目的进度控制是管理知识中的一个难点，涉及建井工期确定、网络方法分析和使用、控制措施与计划调整等。本题的要求是确定属于组织管理措施的一项内容。显然，施工方案、新技术这两项属于技术控制措施，资源计划编制属于资源调配方面的内容，因此可以确定，协调与分包单位关系应是组织管理控制措施。故答案应为C。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]