[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146956":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1146956,801,1,"单选题","矿井井筒施工阶段，进度控制的要点是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","优化井筒施工提升方案，保证井筒施工提升能力",false,{"key":16,"text":17,"correct":14},"B","选用大型抓岩机，加快井筒施工的出渣速度",{"key":19,"text":20,"correct":21},"C","认真处理好主井井筒与装载硐室的施工",true,{"key":23,"text":24,"correct":14},"D","做好主、副井交替装备工作","立井井筒施工阶段的主要工作内容包括井筒施工方案(包括表土和基岩)的确定、井筒施工各项工作的合理组织、井筒施工与相邻硐室施工方案的合理组织，井筒施工装备方案的组织。对于井筒施工方案，重点要做好表土施工方案选择，基岩施工要确保各施工工序能力的配套，提升能力、出渣能力、砌壁速度要合理安排，才能保证施工的正规循环。对于主井井筒，要合理确定井筒与箕斗装载硐室的施工关系，确保箕斗装载硐室的施工不会对总工期产生影响。主、副井交替装备的施工组织要进行合理安排。上述这几个方面，箕斗装载硐室的施工对井筒工期的影响最大，通过调整箕斗装载硐室的施工时间，可以优化整个矿井的施工工期，也是确保井筒施工工期和矿井建设工期的关键。因此，答案选C。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]