[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146954":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1146954,801,1,"单选题","关于矿山工程进度控制中的事中控制内容，正确的说法是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","及时检查与协调",true,{"key":16,"text":17,"correct":18},"B","改变物资供应计划",false,{"key":20,"text":21,"correct":18},"C","及时调整施工计划",{"key":23,"text":24,"correct":18},"D","变更资金供应方式","进度控制中的事中控制内容主要包括工程进度的经常检查；工程进度的动态管理；组织协调会。而编制矿井施工组织设计，确定施工方案、施工总进度计 划、施工总平面图及材料设备的采购供应计划；做好四通一平及障碍物拆迁工作；及时向施工单位提供设计图纸等设计文件等内容属于事前控制内容。而制定总工期目标突破后的补救措施、调整施工计划、材料设备及资金供应，确定新的工期目标等内容属于事后控制。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]