[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146946":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1146946,801,1,"单选题","确定建井工期的方法，通常是根据（ ）来确定。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","累计重要土建、安装工程完成时间",false,{"key":16,"text":17,"correct":18},"B","井巷工程的施工期",true,{"key":20,"text":21,"correct":14},"C","设备的最终到货时间",{"key":23,"text":24,"correct":14},"D","矿建、土建、安装时间总和","目前，确定建井工期的主要方法是根据关键路线的工作内容来进行。具体的推算方法可以有三种。通常以井巷工程的施工期为主要方法，即：按矿井井巷工程在关键路线上的施工期来推算矿井建设工期。如用土建、安装工程工期来考虑，则是要将与井巷工程紧密相连的土建工程，即为主副永久装备系统和地面生产系统与三类工程相连部分的施工期。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]