[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146944":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1146944,801,1,"单选题","下列对网络计划编制的要求中，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","正常的组织关系绝对不能颠倒",true,{"key":16,"text":17,"correct":18},"B","应该一次成功",false,{"key":20,"text":21,"correct":18},"C","唯一要求是满足工期要求",{"key":23,"text":24,"correct":18},"D","必须是最短的工时结果","网络编制首先要明确工程内容、工序及每个工序的估算时间，然后可以将项目的所有工序，依次列成表格，编排序号，以便于查对是否遗漏或重复，并分析相互之间的逻辑制约关系。这是基本材料，一定要正确。所谓逻辑关系在矿山工程中还涉及施工顺序等问题。因此网络编制就应遵循建井工期最短，经济技术合理、施工可行，并在具体工程条件、矿井地质和水文地质条件下可以获得最佳的经济效益的原则。可行的计划不一定是最优的计划。计划的优化是提高经济效益的关键步骤。如果计划的优化程度已经可以令人满意，就得到了可以用来指导施工、控制进度的施工网络图了。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]