[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146942":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1146942,801,1,"单选题","在一个单项工程中有多个承包单位参加施工时，应按（ ）分解进度目标。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","按承包单位",true,{"key":16,"text":17,"correct":18},"B","按时间前后统一",false,{"key":20,"text":21,"correct":18},"C","按施工阶段",{"key":23,"text":24,"correct":18},"D","按施工项目","在一个单项工程中有多个承包单位参加施工时，应按承包单位将单项工程的进度目标分解，确定出各单位的进度目标，列入分包合同，以便落实分包责任，并根据各专业工程交叉施工方案和前后衔接条件，明确不同承包单位工作面交接条件和时间。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]