[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146940":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1146940,801,1,"单选题","关于工程进度的编制，做法正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工期就是各工序延续时间的和",false,{"key":16,"text":17,"correct":14},"B","工序延续时间是工序定额与人力的乘积",{"key":19,"text":20,"correct":21},"C","网络计划的第一步是编制工序表",true,{"key":23,"text":24,"correct":14},"D","网络优化的内容就是缩短工期","工期和各工序延续时间之和不同，工期仅与关键线路上的相关工序有关，与其他线路上的工序时间无关。工序延续时间显然不是工序产量的定额值与人力的乘积，这仅是单位时间的工作量。网络优化的内容很多，包括进一步优化的可能性、可行性判断、资源配备及调配等。网络编制首先是落实工序内容，明确有哪些工序参与了该工程及其延续时间。所以答案应是C。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]