[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146939":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1146939,801,1,"单选题","矿业工程在确定工期过程中，做法不合理的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","要同时明确协调内容和关系",false,{"key":16,"text":17,"correct":14},"B","要因地制宜，量力而行",{"key":19,"text":20,"correct":14},"C","合理配备所需资源",{"key":22,"text":23,"correct":24},"D","总工期必须大于合同工期",true,"矿业工程项目工期确定时要注意：(1)合理安排土建与安装的综合施工；(2)因地制宜，量力而行；(3)配备所需资源；(4)考虑外部条件的配合情况，包括施工所需施工图纸、水、电、气、道路及业主所提供的工程设备、材料到货情况，天气情况，注意冬、雨期等影响。最终所确定的建设工期必须满足合同工期要求。因此，总工期大于合同工期是不合理的。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]